色婷婷五月综合亚洲小说-国产精品久aaaaa片-在线亚洲97se亚洲综合在线-欧美三级午夜理伦三级-亚洲超清无码制服丝袜无广告

Brief Introduction, Construction Steps and Physical Properties of MPP Power Pipe

2025-03-21

First, construction instructions

1, MPP power pipe transportation, construction process is strictly prohibited arbitrary throwing, impact, marking, exposure.

2, MPP power pipe hot melt butt two tube axis should be aligned, the end face cutting to be vertical flat.

3, Wuhan MPP power pipe processing temperature, time, pressure, depending on the climate conditions to adjust accordingly.

4, MPP power pipe pipe minimum bending radius should be 75% of the outer diameter of the pipe.

5, Hubei MPP power casing standard fixed length (6 meters, 9 meters) pipe configuration pillow 3 pay, pipe pillow spacing of 2.0m, pipe pillow from the joint is 0.5m.

2. Construction method

(1) The preparatory work stage before construction, that is, organize technicians to re-test the plane control points and leveling points delivered by the owner, set temporary leveling points at a distance of about 150 meters, and close them with the elevation reference point. The closure difference is less than the specification requirements. The elevation control baseplate elevation is measured by BJD23 automatic leveling level. The construction control network and the starting point of the construction level should be set in a place that is not disturbed, firm and reliable, and has good visibility conditions, which is easy to control. On the premise of matching the elevation of the sidewalk with the elevation, the project and the main road should also be considered.

(2) The trench construction is based on the local obedience to the whole, creating conditions for the overall appearance.

1, trench earth excavation

① The trench construction adopts trapezoidal fracture, section excavation, mainly mechanical, manual cooperation. Adopt straight groove form of excavation. Strictly control the design elevation of the bottom of the trench during excavation, and the mechanical excavation should keep 10cm with manual bottom cleaning to avoid mechanical overexcavation disturbing the original soil at the bottom of the trench. If you encounter bad soil, report it in writing to the owner and the supervision engineer, and then make construction treatment after approval.

② Do a good job of foundation pit drainage during excavation, and the maximum area of 15cm 15cm symmetrical on both sides of the drainage ditch is appropriate. Before and during construction, the exclusion of surface water and the recruitment and drainage of water accumulation in the base are tested to ensure that the base plate of the condenser is constructed in a waterless environment. During the excavation of the foundation pit, no abandoned soil and building materials are piled up near Jihang, so as to achieve civilized construction. When excavating the foundation pit, if bad soil is encountered, the slope should be appropriately increased to ensure the working surface at the bottom of the groove.

2. Before the construction of the trench concrete baseplate, level the trench baseplate, release the trench center line, and use the trench soil mold to pour the concrete baseplate according to the designed height and width. The concrete is labeled C15, and the commercial concrete is used with a thickness of 10cm. When pouring, vibrate strictly according to the requirements until it is completely dense. After pouring, light collection and timely maintenance are carried out to ensure the strength of the concrete. The trench baseplate should be 3% sloped in the direction of drainage, so as to drain the cable trench.

3, the laying of the cable pipe is tiled on the concrete baseplate with a 10cm thick medium sand cushion, and then laying the cable pipe, and filling the gap between the pipes with sand, tamping with wooden sticks, so that the sand forms an arc-shaped pipe bed on the outer wall of the pipe. When laying the pipe, the joints of each section should be staggered to ensure that the connection is tight and no sand can penetrate. After the pipe group is laid, an 8 #iron wire is penetrated into each hole for future threading. According to the construction requirements, lay the pipe layer by layer, and wait for the top. After the layer of pipe is laid, lay a 10cm thick medium sand cushion.

4, the earth backfill step settles, so that the sand and the cable pipe form a dense whole. After the telephone row has been laid, the earth return is carried out, mainly mechanical and manual cooperation. Layered backfill, the thickness of each layer is 15cm, the well is tamped, and the height of the backfill matches the elevation of the main road surface. The remaining soil is transported to the residual soil disposal site by dump truck.

3. Physical properties

Technical performance items Technical performance indicators Test method Density 0.90~ 0.94GB/T1033.1 Ring stiffness (3% room temperature) SN24 grade ? 24GB/T9647-2015SN32 grade ? 32SN40 grade ? 40 Flattening test When the vertical deformation of the pattern is 50% of the original inner diameter, the

style should not crack or crack

DL/T802.7-2010 Drop hammer impact pattern should not crack or crack DL/T802.7-2010 Vicat softening temperature ? 150 ℃ GB/T-1633-2000 Tensile strength Pipe: ? 25;

Welded joint: ? 22.5

GB/T8804.3-2003 Elongation at break ? 400% GB/T8804.3-2003 Bending strength ? 36MPaGB/T9341-2000MPP power pipe is a customized product, Wuhan MPP power pipe, Hubei MPP power pipe manufacturer is Hubei Yuyuan Building We have a number of high-speed production lines, which are faster than the production speed of ordinary manufacturers. Generally, contact us to customize MPP pipelines, which can be delivered within one to three days, which can effectively ensure the construction progress.

Source: Hubei AD Building Materials Co., Ltd., welcome to share! Hotline: 17399989993

Brief Introduction, Construction Steps and Physical Properties of MPP Power Pipethe1page


主站蜘蛛池模板: 男人的好看免费观看在线视频| 久久婷婷丁香七月色综合| 麻豆国产av丝袜白领传媒 | 人妻人人澡人人添人人爽| 日韩精品无码熟人妻视频| 国产精品亚洲精品日韩己满十八小| 久久久久久久岛国免费观看| 久久午夜福利电影| 好吊妞视频这里有精品| 国产在视频精品线观看| 四虎国产精品永久地址49| 国产精选污视频在线观看| 亚洲精品久久久久久久久久吃药 | 99视频精品全部免费 在线 | 黑人巨大精品欧美| 国产好大好硬好爽免费不卡| 亚洲AV无码乱码精品| 人妻免费一区二区三区最新| 日本xxxx色视频在线播放| 成人美女黄网站色大免费的| 无码天堂亚洲国产av| 国产午夜激无码av毛片不卡| 强睡邻居人妻中文字幕| 欧美白丰满老太aaa片| 国产成人年无码av片在线观看| 三级国产三级在线| 亚洲欧洲日韩在线电影| 日日躁夜夜躁狠狠躁| 国内盗摄视频一区二区三区| 精品无码中文字幕在线| 中文字幕久久综合伊人| 少妇和邻居做不戴套视频| 欧美又大又硬又粗bbbbb| 午夜福利电影无码专区| 国产精品久久久久秋霞鲁丝 | 国内精品久久久久久99蜜桃| 免费无码又爽又刺激网站| 中文字幕美人妻亅u乚一596| 免费网站观看www在线观看| 亚洲欭美日韩颜射在线| 丰满人妻熟妇乱又伦精品软件 |