日韩hdI久操天堂I久草在线费播放视频I依人做aI强开小受嫩苞第一次免费视频I鲁一鲁在线I亚洲淫小说AV在线I绿帽 无套 91 九色 论坛I大香焦超碰I国产96视频I久久免费的精品国产v∧I五月天婷婷综合I可以免费看av的网站I欧洲精品码一区二区三区免费看I日本二三四区I日韩黄色一级电影I99爱精品视频在线观看I特级西西www44高清大胆图片

Brief Introduction, Construction Steps and Physical Properties of MPP Power Pipe

2025-03-21

First, construction instructions

1, MPP power pipe transportation, construction process is strictly prohibited arbitrary throwing, impact, marking, exposure.

2, MPP power pipe hot melt butt two tube axis should be aligned, the end face cutting to be vertical flat.

3, Wuhan MPP power pipe processing temperature, time, pressure, depending on the climate conditions to adjust accordingly.

4, MPP power pipe pipe minimum bending radius should be 75% of the outer diameter of the pipe.

5, Hubei MPP power casing standard fixed length (6 meters, 9 meters) pipe configuration pillow 3 pay, pipe pillow spacing of 2.0m, pipe pillow from the joint is 0.5m.

2. Construction method

(1) The preparatory work stage before construction, that is, organize technicians to re-test the plane control points and leveling points delivered by the owner, set temporary leveling points at a distance of about 150 meters, and close them with the elevation reference point. The closure difference is less than the specification requirements. The elevation control baseplate elevation is measured by BJD23 automatic leveling level. The construction control network and the starting point of the construction level should be set in a place that is not disturbed, firm and reliable, and has good visibility conditions, which is easy to control. On the premise of matching the elevation of the sidewalk with the elevation, the project and the main road should also be considered.

(2) The trench construction is based on the local obedience to the whole, creating conditions for the overall appearance.

1, trench earth excavation

① The trench construction adopts trapezoidal fracture, section excavation, mainly mechanical, manual cooperation. Adopt straight groove form of excavation. Strictly control the design elevation of the bottom of the trench during excavation, and the mechanical excavation should keep 10cm with manual bottom cleaning to avoid mechanical overexcavation disturbing the original soil at the bottom of the trench. If you encounter bad soil, report it in writing to the owner and the supervision engineer, and then make construction treatment after approval.

② Do a good job of foundation pit drainage during excavation, and the maximum area of 15cm 15cm symmetrical on both sides of the drainage ditch is appropriate. Before and during construction, the exclusion of surface water and the recruitment and drainage of water accumulation in the base are tested to ensure that the base plate of the condenser is constructed in a waterless environment. During the excavation of the foundation pit, no abandoned soil and building materials are piled up near Jihang, so as to achieve civilized construction. When excavating the foundation pit, if bad soil is encountered, the slope should be appropriately increased to ensure the working surface at the bottom of the groove.

2. Before the construction of the trench concrete baseplate, level the trench baseplate, release the trench center line, and use the trench soil mold to pour the concrete baseplate according to the designed height and width. The concrete is labeled C15, and the commercial concrete is used with a thickness of 10cm. When pouring, vibrate strictly according to the requirements until it is completely dense. After pouring, light collection and timely maintenance are carried out to ensure the strength of the concrete. The trench baseplate should be 3% sloped in the direction of drainage, so as to drain the cable trench.

3, the laying of the cable pipe is tiled on the concrete baseplate with a 10cm thick medium sand cushion, and then laying the cable pipe, and filling the gap between the pipes with sand, tamping with wooden sticks, so that the sand forms an arc-shaped pipe bed on the outer wall of the pipe. When laying the pipe, the joints of each section should be staggered to ensure that the connection is tight and no sand can penetrate. After the pipe group is laid, an 8 #iron wire is penetrated into each hole for future threading. According to the construction requirements, lay the pipe layer by layer, and wait for the top. After the layer of pipe is laid, lay a 10cm thick medium sand cushion.

4, the earth backfill step settles, so that the sand and the cable pipe form a dense whole. After the telephone row has been laid, the earth return is carried out, mainly mechanical and manual cooperation. Layered backfill, the thickness of each layer is 15cm, the well is tamped, and the height of the backfill matches the elevation of the main road surface. The remaining soil is transported to the residual soil disposal site by dump truck.

3. Physical properties

Technical performance items Technical performance indicators Test method Density 0.90~ 0.94GB/T1033.1 Ring stiffness (3% room temperature) SN24 grade ? 24GB/T9647-2015SN32 grade ? 32SN40 grade ? 40 Flattening test When the vertical deformation of the pattern is 50% of the original inner diameter, the

style should not crack or crack

DL/T802.7-2010 Drop hammer impact pattern should not crack or crack DL/T802.7-2010 Vicat softening temperature ? 150 ℃ GB/T-1633-2000 Tensile strength Pipe: ? 25;

Welded joint: ? 22.5

GB/T8804.3-2003 Elongation at break ? 400% GB/T8804.3-2003 Bending strength ? 36MPaGB/T9341-2000MPP power pipe is a customized product, Wuhan MPP power pipe, Hubei MPP power pipe manufacturer is Hubei Yuyuan Building We have a number of high-speed production lines, which are faster than the production speed of ordinary manufacturers. Generally, contact us to customize MPP pipelines, which can be delivered within one to three days, which can effectively ensure the construction progress.

Source: Hubei AD Building Materials Co., Ltd., welcome to share! Hotline: 17399989993

Brief Introduction, Construction Steps and Physical Properties of MPP Power Pipethe1page


主站蜘蛛池模板: 99久久无码一区人妻a黑| 性欧美老人牲交xxxxx视频| 国产一区二区色婬影院| 亚洲色婷婷久久精品av蜜桃 | 精品综合久久久久久8888| 天堂无码人妻精品一区二区三区| 成人午夜福利视频后入| 国产强被迫伦姧在线观看无码| 2021国产精品香蕉在线观看| 国产精品高清一区二区不卡| 深夜福利小视频在线观看| 久久久网站| 精品欧洲av无码一区二区三区| 国产拍揄自揄精品视频| 久久久国产精华液| 亚洲无线看天堂av| 人妻少妇被粗大爽9797pw| 久久九九久精品国产免费直播| 亚洲精品久久久久久中文| 国产精品v片在线观看不卡| 成年奭片免费观看视频天天看| 亚洲国产精品无码久久一线| 日日摸处处碰夜夜爽| 激情射精爆插热吻无码视频| 久久综合精品国产一区二区三区无 | 免费人成视频x8x8入口| 99精品热这里只有精品| 久久国产乱子精品免费女| 宅女午夜福利免费视频| 一本色道久久东京热| 精品无码国产av一区二区三区| 亚洲最大成人一区久久久| 东北妇女精品bbwbbw| 国产成人综合美国十次| 国产亚洲曝欧美曝妖精品| 四库影院永久国产精品地址| 国产精品国产精品国产专区不卡| 久久东京伊人一本到鬼色| 丰满少妇高潮惨叫正在播放| 国产在线观看www污污污| 18禁在线永久免费观看|