日韩hdI久操天堂I久草在线费播放视频I依人做aI强开小受嫩苞第一次免费视频I鲁一鲁在线I亚洲淫小说AV在线I绿帽 无套 91 九色 论坛I大香焦超碰I国产96视频I久久免费的精品国产v∧I五月天婷婷综合I可以免费看av的网站I欧洲精品码一区二区三区免费看I日本二三四区I日韩黄色一级电影I99爱精品视频在线观看I特级西西www44高清大胆图片

How to Construction HDPE Double Wall Corrugated Pipe

2025-03-19

How to Construction HDPE Double Wall Corrugated Pipethe1page

before excavating the pipeline trench, conduct a comprehensive understanding of the geological conditions of the construction site, groundwater conditions, and design requirements of the rain and sewage system, and reasonably determine the buried depth of the pipeline and the treatment method of the foundation. Among them, the most important work is to verify the bearing capacity of the foundation foundation. If it does not meet the construction requirements, it should be dealt with through measures such as replacement and stone throwing to improve the bearing capacity of the foundation. After preparing for construction, the trench should be mined according to the pipeline construction plan. The geometric dimensions of the trench should conform to the design plan. If there are loose stones and earth blocks at the bottom of the trench, it should be removed, and a sand cushion should be laid on it to compact and level, so as to avoid hard objects from damaging the Wuhan HDPE double-wall corrugated pipe.

2. Install

to install the HDPE double-wall corrugated pipe. Review the depth, width, and bottom standard of the trench. After confirming that there is no gravel, broken soil, etc. in the trench, the installation work is officially started. HDPE double-wall corrugated pipe itself is not of high quality. Generally, large-scale hoisting devices are not required. If the buried depth of the pipeline is less than 3.0m and the diameter is lower than DN500, the lower pipe can be manually used. If the buried depth of the pipeline is higher than 3.0m and the diameter is higher than DN500, the hoisting installation method needs to be adopted. When hoisting and installing, the pipeline should be smooth when it is lowered to the bottom of the trench and cannot disturb the foundation. When it is necessary to cut the pipeline, the pipeline section should be vertical and flat, and the pipeline itself cannot be damaged. When installing, pay attention to the following points: First, the pipeline should be laid in a straight line. If it needs to be laid in a folded line, the relative corner should not be greater than 2; Second, after the pipeline is lowered, the drainage in the groove should be good, and there should be no water accumulation to prevent electric shock accidents; Third, the interface between the pipe and the pipe should leave a certain space to facilitate subsequent connection.

Third, the connection methods of connecting

HDPE double-wall corrugated pipe mainly include heat shrinkage sleeve connection, electric hot melt belt connection, etc., and their respective operation points are different. In the heat shrinkage sleeve connection method, first clean up the moisture and debris on the surface of the pipe, use the heat shrinkage belt to tightly wrap the pipe joint part, and use a flame gun to slightly bake the heat shrinkage belt and the pipe contact part. After that, wrap the baked heat shrinkable tape with another heat shrinkable tape, clamp it tightly, and then bake it with a flame gun at the part where the heat shrinkable tape is wrapped, first up and down, then left and right, so that the heat shrinkable tape is completely close to the pipe. In the connection mode of the electric hot melt belt, the surface of the pipe should also be cleaned first, the joint part should be wrapped with the electric hot melt belt, and the buckle belt should be fastened. Connect the electric hot melt belt to the electric hot melt machine, set the current intensity and heating time. After the electric hot melt is completed, fasten the buckle belt again and cool for a period of time. After checking that the connection quality meets the standard requirements, release the buckle belt. In addition to the connection between the pipe and the pipe, the connection between the Wuhan

Jingjie HDPE double-wall corrugated pipe and the well should also be paid attention to. HDPE double-wall corrugated pipe first goes deep into the well from the pipe trench, and the pipe is propped up with a support device to prevent concentrated load or shearing. Common way of connecting HDPE double-wall corrugated pipe with the well wall: Apply polyvinyl chloride adhesive at the connection between HDPE double-wall corrugated pipe and the well wall, lay a layer of fine sand on it, penetrate the pipe into the well wall, and use cement mortar to build and block.

4. Water closure test

After the pipeline is connected, conduct a water closure test to confirm whether the tightness of the pipeline in the water injection situation meets the requirements. First, check whether there is blockage, water accumulation, etc., inside the pipeline. After confirming that there is no above situation, inject water into the pipeline. After water injection, keep it for a period of time. If the scale of the pipeline project is large and it is impossible to implement the closed water test one by one, the closed water test pipeline can be determined by sampling. If water seepage or leakage is found, the test should be stopped immediately, the pipeline connection should be re-carried out, and the closed water test should be carried out again.

Fifth, backfill

After completing the above work, start the backfill work. Backfill from the connection part of the pipeline and the foundation first. The method adopts a symmetrical form. It is forbidden to backfill on one side and then backfill on the other side. The symmetrical method is also used for tamping to reduce the impact on the pipeline and avoid the deformation of the pipeline. When backfilling, a layered filling method is used, and the thickness of each layer of backfill soil is controlled between 0.15m and 0.20m. The thickness of the backfill soil layer at the top of the pipeline is about 0. If conditions permit, mechanical rolling can be used to ensure that the compaction of the backfill meets the design requirements.

This article is reproduced on the Internet and is only used for technical research and sharing. If there is any infringement, please contact us to delete it. Wuhan corrugated pipe, Hubei double-wall corrugated pipe, AD pe double-wall corrugated pipe, Jingjie HDPE double-wall corrugated pipe, Yonggao corrugated pipe can contact us.


主站蜘蛛池模板: 欧美日韩亚洲精品瑜伽裤| 国产二级一片内射视频播放| 中文字幕人妻熟女人妻a片| 小荡货奶真大水真多紧视频| 色综合久久久久综合一本到桃花网 | 久久天天躁狠狠躁夜夜2020老熟妇| 婷婷久久综合九色综合绿巨人| 夜夜添无码一区二区三区 | 亚洲最大激情中文字幕| 99久久人妻精品免费一区| 久久国内精品一区二区三区| 人人妻人人澡人人爽久久av| 国模少妇一区二区三区| 久久久噜噜噜久久免费| 最新中文字幕av无码不卡| 欧美变态口味重另类在线视频| 国产成人精品日本亚洲语音| 亚洲一区二区三区高清在线看| 久久国产亚洲精选av| 成人免费午夜福利片在线观看| 久久97超碰色中文字幕| 男女啪啪永久免费网站| 久久精品人妻少妇一区二区三区| 久久精品国产一区二区三区| 亚瑟av亚洲精品一区二区| 久久精品成人免费观看| 一区二区国产高清视频在线| 无码福利在线观看1000集| 被窝影院午夜无码国产| 99久久99久久精品国产片| 性欧美牲交xxxxx视频欧美 | 国产亚洲一区二区手机在线观看 | 久久青青草原一区二区| 无码精品a∨动漫在线观看| 国产成人精品亚洲精品| 国产美女视频免费的| 高h纯肉大尺度调教play| 日韩国产图片区视频一区| 日韩国产图片区视频一区| 波多野结衣一区二区三区高清| 国产成人综合亚洲精品|