日韩hdI久操天堂I久草在线费播放视频I依人做aI强开小受嫩苞第一次免费视频I鲁一鲁在线I亚洲淫小说AV在线I绿帽 无套 91 九色 论坛I大香焦超碰I国产96视频I久久免费的精品国产v∧I五月天婷婷综合I可以免费看av的网站I欧洲精品码一区二区三区免费看I日本二三四区I日韩黄色一级电影I99爱精品视频在线观看I特级西西www44高清大胆图片

How to Construction HDPE Double Wall Corrugated Pipe

2025-03-19

How to Construction HDPE Double Wall Corrugated Pipethe1page

before excavating the pipeline trench, conduct a comprehensive understanding of the geological conditions of the construction site, groundwater conditions, and design requirements of the rain and sewage system, and reasonably determine the buried depth of the pipeline and the treatment method of the foundation. Among them, the most important work is to verify the bearing capacity of the foundation foundation. If it does not meet the construction requirements, it should be dealt with through measures such as replacement and stone throwing to improve the bearing capacity of the foundation. After preparing for construction, the trench should be mined according to the pipeline construction plan. The geometric dimensions of the trench should conform to the design plan. If there are loose stones and earth blocks at the bottom of the trench, it should be removed, and a sand cushion should be laid on it to compact and level, so as to avoid hard objects from damaging the Wuhan HDPE double-wall corrugated pipe.

2. Install

to install the HDPE double-wall corrugated pipe. Review the depth, width, and bottom standard of the trench. After confirming that there is no gravel, broken soil, etc. in the trench, the installation work is officially started. HDPE double-wall corrugated pipe itself is not of high quality. Generally, large-scale hoisting devices are not required. If the buried depth of the pipeline is less than 3.0m and the diameter is lower than DN500, the lower pipe can be manually used. If the buried depth of the pipeline is higher than 3.0m and the diameter is higher than DN500, the hoisting installation method needs to be adopted. When hoisting and installing, the pipeline should be smooth when it is lowered to the bottom of the trench and cannot disturb the foundation. When it is necessary to cut the pipeline, the pipeline section should be vertical and flat, and the pipeline itself cannot be damaged. When installing, pay attention to the following points: First, the pipeline should be laid in a straight line. If it needs to be laid in a folded line, the relative corner should not be greater than 2; Second, after the pipeline is lowered, the drainage in the groove should be good, and there should be no water accumulation to prevent electric shock accidents; Third, the interface between the pipe and the pipe should leave a certain space to facilitate subsequent connection.

Third, the connection methods of connecting

HDPE double-wall corrugated pipe mainly include heat shrinkage sleeve connection, electric hot melt belt connection, etc., and their respective operation points are different. In the heat shrinkage sleeve connection method, first clean up the moisture and debris on the surface of the pipe, use the heat shrinkage belt to tightly wrap the pipe joint part, and use a flame gun to slightly bake the heat shrinkage belt and the pipe contact part. After that, wrap the baked heat shrinkable tape with another heat shrinkable tape, clamp it tightly, and then bake it with a flame gun at the part where the heat shrinkable tape is wrapped, first up and down, then left and right, so that the heat shrinkable tape is completely close to the pipe. In the connection mode of the electric hot melt belt, the surface of the pipe should also be cleaned first, the joint part should be wrapped with the electric hot melt belt, and the buckle belt should be fastened. Connect the electric hot melt belt to the electric hot melt machine, set the current intensity and heating time. After the electric hot melt is completed, fasten the buckle belt again and cool for a period of time. After checking that the connection quality meets the standard requirements, release the buckle belt. In addition to the connection between the pipe and the pipe, the connection between the Wuhan

Jingjie HDPE double-wall corrugated pipe and the well should also be paid attention to. HDPE double-wall corrugated pipe first goes deep into the well from the pipe trench, and the pipe is propped up with a support device to prevent concentrated load or shearing. Common way of connecting HDPE double-wall corrugated pipe with the well wall: Apply polyvinyl chloride adhesive at the connection between HDPE double-wall corrugated pipe and the well wall, lay a layer of fine sand on it, penetrate the pipe into the well wall, and use cement mortar to build and block.

4. Water closure test

After the pipeline is connected, conduct a water closure test to confirm whether the tightness of the pipeline in the water injection situation meets the requirements. First, check whether there is blockage, water accumulation, etc., inside the pipeline. After confirming that there is no above situation, inject water into the pipeline. After water injection, keep it for a period of time. If the scale of the pipeline project is large and it is impossible to implement the closed water test one by one, the closed water test pipeline can be determined by sampling. If water seepage or leakage is found, the test should be stopped immediately, the pipeline connection should be re-carried out, and the closed water test should be carried out again.

Fifth, backfill

After completing the above work, start the backfill work. Backfill from the connection part of the pipeline and the foundation first. The method adopts a symmetrical form. It is forbidden to backfill on one side and then backfill on the other side. The symmetrical method is also used for tamping to reduce the impact on the pipeline and avoid the deformation of the pipeline. When backfilling, a layered filling method is used, and the thickness of each layer of backfill soil is controlled between 0.15m and 0.20m. The thickness of the backfill soil layer at the top of the pipeline is about 0. If conditions permit, mechanical rolling can be used to ensure that the compaction of the backfill meets the design requirements.

This article is reproduced on the Internet and is only used for technical research and sharing. If there is any infringement, please contact us to delete it. Wuhan corrugated pipe, Hubei double-wall corrugated pipe, AD pe double-wall corrugated pipe, Jingjie HDPE double-wall corrugated pipe, Yonggao corrugated pipe can contact us.


主站蜘蛛池模板: 无码无需播放器av网站| 中文字幕免费不卡二区| 亚洲一卡二卡三卡四卡| 无码专区一ⅴa亚洲v专区在线| 夜夜躁日日躁狠狠久久av| 日本精品无码一区二区三区久久久| 天天天天噜在线视频| 一本到中文无码av在线精品| 亚洲中字慕日产2020| 综合激情久久综合激情| 少妇久久久久久人妻无码| 人人超人人超碰超国产| 精品爆乳一区二区三区无码av | 天干天干天啪啪夜爽爽99| 春色校园亚洲愉拍自拍| 中文字幕精品亚洲无线码二区| 成人亚洲欧美日韩在线观看 | 天堂8在线天堂资源bt| 亚洲性色成人av天堂| 国产成人久久777777| 中国老熟女重囗味hdxx| 狠狠躁夜夜躁人人爽蜜桃| 极品粉嫩福利午夜在线播放| 欧美日韩不卡合集视频| 亚洲永久无码3d动漫一区| 久久精品久久精品久久39| 国内大量偷窥精品视频| 日韩一卡2卡3卡4卡新区亚洲 | 伊在人亚洲香蕉精品区麻豆 | 岛国在线无码高清视频| 久久香蕉成人免费大片| 色综合久久综合欧美综合网| 日本少妇浓毛bbwbbwbbw| 免费萌白酱国产一区二区三区| 久久99精品国产麻豆婷婷| 嫖妓丰满肥熟妇在线精品| 欧美人与动牲交欧美精品 | 亚洲成av人片久久| 国内精品久久久久久不卡影院| 国产精品国产自线拍免费| 人人曰人人做人人|